Oct 12, 2009
Hydro Quebec Strategic Plan 2009-2013
Here are some excerpts from Hydro Quebec's Strategic Plan 2009-2013 concerning rivers along the North Coast.
-The Romaine Complex will enable Hydro Québec Production to increase its exports to markets outside Québec.
-One of these projects is located on the Petit Mécatina, some 250 km east of the Romaine. The company has already carried out the preliminary studies and some field surveys. Draft-design studies are set to begin in 2009. These will allow us to determine the final configuration, features and cost of the facilities, and carefully assess their environmental impacts. The working hypothesis calls for two generating stations (Petit-Mécatina-3 and Petit-Mécatina-4) with a total capacity of 1,200 MW.
-Other projects totaling more than 1,750MW round out this first group. They include Tabaret generating station, which is planned near Kipawa dam in the Témiscamingue region, and another project to be built on the Magpie; both of these have yet to undergo a detailed environmental assessment. The addition of a third generating unit at Sainte-Marguerite-3 is also being considered, along with refits that would yield capacity gains at Manic-2 (commissioning: 2013 to 2016) and Manic-3 (commissioning: after 2015).
-NORTHERN PLAN
3,500 MW BY 2035
3,000 MW of hydropower
300 MW of wind power
200 MW of emerging renewables
-Hydro-Québec Production has been present on wholesale markets in the Northeast since 1999, and now wants to extend its sales activities to the U.S. Midwest.